Mainstream
Dry Hydrants Incorporated. Ph. (613) 622-0990
E-mail :
Mike@dryhydrants.com
www.dryhydrants.com |
More Photo's |
|
Installing a Dry Hydrant
|
Site Selection: |
|
|
Your intake strainer
should be located at least eighteen inches off the bottom to avoid
sediment and at least twenty four inches below the waters surface at
low water to avoid cavitation. Ice depth must be taken into account
in areas of Winter freeze-up. In our latitude we can get three,
sometimes up to four feet of ice forming on calm water so I like a
site with a minimum depth of seven feet at low water. This puts the
strainer five feet below the surface. A portable depth sounder is a
handy tool for the site selection and planning process. The
rise, or lift, from the waters surface to the top of the hydrant
head should be kept under 16 feet for properly maintained "class A"
fire service pumps.
Don't forget to consider an easement agreement if your hydrant is to
be installed on someone else's property. |
Permits and silt screening: |
|
|
may be required in your area to protect the
environment and fish habitat. Fish will not spawn on sand or silt.
The silt from the excavation can settle over great distances
underwater, so the excavation and equipment should remain inside a
silt screen barrier. Any equipment entering the water should be
clean and free of oil. Fuelling must be done well away from the
waters edge. Rock, (rip rap) has been recommended as a top dressing
to the underwater excavation as the fish will spawn on
rocks. Check with your local authorities. |
Installation: |
|
|
The schedule 40 or 80 PVC pipe
should be assembled at least 24 hours in advance of trenching to
allow all glue joints to cure. But don't leave pipe laying around
for weeks because it is susceptible to degradation by the sun’s
ultra violet rays. Each joint should be cleaned and prepped with a
clean dry cloth then lightly scuffed with sandpaper to remove gloss
then cleaned again. Both joints should then be primed and liberally
coated with heavy duty PVC glue. Note instructions on
container regarding minimum and maximum working temperature and
please observe cautionary notes. You have a matter of seconds before
the bond begins so have some assistants on hand to wrestle the pipe
joints together. The joint, once made must be held in place for at
least 30 seconds so the exothermic reaction set off by the glue and
primer can't push the two sections apart. Don't attach the hydrant
adapter at this time, leave the riser a little longer than required
and cut it off after the finished grade elevation is established.
Once the rise and run of the pipe has been assembled and allowed to
cure for approx. 24 hours the trench can be excavated. The depth of
the trench must be consistently close to level from where it begins
out in the water to where it ends just beyond the location of the
riser. The most important consideration is that the horizontal run
of pipe always remains under water. Prior to installation the
strainer can be bagged and taped with a green garbage so that the
whole system may be floated into position. The pipe is then lowered
into the trench by ropes attached along the length of it and handled
by an adequate number of assistants from both sides of the trench.
(No-one should be allowed in or near the trench at any time as
wet and sandy soil conditions are prone to collapse.) The riser
should be roped at the bottom and top from both sides to allow
proper placement while backfilling. Once in position a skilled
individual in a small boat can remove the bag from the strainer. At
this time the riser should be held high in the water to allow all
air to escape from the pipe as it sinks. It is recommended to fill
below and around the pipe with gravel to help protect the pipe
before backfilling. Don't let the equipment operator push down on
the pipe or pack the fill with his shovel until the whole pipe is
well covered with the fill material. An uneven bottom can stress and
bend the pipe under the force of the shovel and result in changing
the elevation of the strainer or breaking the pipe joints.
When the trench is filled the riser can be cut to about 24" above
the finished grade. Most importantly the hydrant adapter should
be installed at an elevation that is below the intake of the
responding pumper. All exposed p.v.c. (above ground) can then be
scuffed with a wire brush, cleaned, primed and painted with acrylic
enamel or epoxy based paint, one coat primer and two coats paint for
u.v. protection. Tremclad spray paint also seems to work well. Six
inch pipe performs well in lengths up to about 65 feet; longer
installations should utilize larger pipe diameters. Where required
the strainer is supported by inserting a 1 inch pipe through the
existing holes and installing a strainer support clamp. |
|
|
In areas of Winter freeze-up: |
|
|
We use two inches of fibre-glass pipe insulation
on the riser, above the water line, wrapped in 6 mil poly and
taped with sheathing tape and sealed with polyurethane caulking to
keep it dry. (Wet fibre-glass loses its insulating ability.) This
helps contain some of the heat loss from the water source and
ground. Styrofoam pipe wrap is preferred. Where insulation is used
and where damage to your hydrant is a concern a sono tube and
concrete can be installed around the exposed pipe for protection. As
an alternative a larger diameter pipe and cap can be used as
protection instead of concrete. This outer protective layer should
also be painted for maximum visibility and u.v. protection. Bollards
can be installed to protect the pipe and a chain hung between the
two will support the pumper truck hard suction hose and prevent
damage to the dry hydrant connection. |
*Important* *Care
must be taken to ensure a safe site as wet soil conditions are prone
to cave-in. No-one is to be
allowed in or near the trench. Your pipe should be
assembled and ready to go in by rope just as soon as the trench is
done. |
*Please
Note* As all sites are
unique and these tips are meant only as general information and cannot
take the place of an experienced installer. All content copyright 2005 - 2022 by: Mike Swarbrick &
Mainstream
Dry Hydrants Inc. |